Explanations of DIN EN ISO 45001:2023 (text version ISO 45001:2018)
Source is DIN EN ISO 45001:2023-12, the German version EN ISO 45001:2023. Title: Occupational health and safety management systems —…
Read articleISO 45001
For: V, IA, EA
Source: DIN EN ISO 45001:2023-12, German, text version ISO 45001:2018. 10.1, 10.2, 10.3, terms 3.34, 3.35, 3.36, 3.37. Annex A.10 as guidance. English for cross-checking.
Clause 10 of this document has three parts. 10.1 is general. 10.2 deals with incident, nonconformity and corrective action. 10.3 is continual improvement. ISO 9001:2026 and ISO 14001:2026 begin clause 10 with continual improvement and deal with nonconformity afterwards. That is the arrangement of those editions. Here, 10.1, 10.2 and 10.3 apply.
A nonconformity, 3.34, is non-fulfilment of a requirement. Note 1 to the term: this relates to requirements of this document and to additional OH&S management system requirements that the organization sets for itself.
An incident, 3.35, is an occurrence arising out of or in the course of work that results, or could result, in injury and ill health. Note 1: an incident in which injury and ill health occur is sometimes referred to as an accident. Note 2: an incident without injury and ill health, but in which that possibility exists, may be referred to as a near miss or a critical situation. “Darf” concerns the designation. Note 3:
Although an incident can be associated with one or more nonconformities, an incident can also occur without a nonconformity being present.
An incident is therefore not a nonconformity under another name. It can be connected with one. It can occur without one.
Corrective action, 3.36, is action to eliminate the causes of a nonconformity or of an incident and to prevent recurrence. The note to the term says that the base definition has been changed and that it also covers incidents, because incidents are a key factor for occupational health and safety, while the actions to remedy them are the same as for nonconformities, namely corrective action. The same kind of action is not the same thing. The definition names both.
Continual improvement, 3.37, is a recurring activity to enhance performance. Note 1: this concerns the use of the system in order to improve overall OH&S performance, consistent with the policy and the objectives. Note 2: “fortlaufend” does not mean “stetig”. The activity need not take place in all areas at the same time.
10.1 requires opportunities for improvement to be determined, with a reference to clause 9, and the necessary actions to be carried out in order to achieve the intended outcomes.
10.2 requires processes that include reporting, investigation and the taking of action, in order to determine and address incidents and nonconformities.
When an incident or a nonconformity occurs, the organization shall:
a) react in a timely manner and, as applicable in each case, take action to control and to correct it, and deal with the consequences;
b) with the participation of workers (5.4) and the involvement of other relevant interested parties, evaluate the need for corrective action so that the causes are eliminated and the incident or the nonconformity does not recur or occur elsewhere. This is done by investigating the incident or reviewing the nonconformity, by determining the causes, and by determining whether something comparable has occurred, exists, or could occur;
c) review the existing assessments of OH&S risks and other risks, as appropriate (6.1);
d) determine and carry out any action required, including corrective action, in accordance with the hierarchy of controls (8.1.2) and the management of change (8.1.3);
e) assess the OH&S risks related to new or changed hazards before action is taken;
f) review the effectiveness of any action taken, including corrective actions;
g) change the system if necessary.
Corrective actions shall be appropriate to the effects, or potential effects, of the incidents or nonconformities that have occurred.
The organization shall communicate the documented information on this to the workers concerned, where they exist to their representatives, and to other relevant interested parties. The note says that reporting and investigation without undue delay could eliminate hazards as quickly as possible and minimize the associated OH&S risks. “Können”. 10.2 does not name a time limit in days. “Rechtzeitig” stands in 10.2 a.
A.10.2, guidance: depending on the requirements of the organization, there may be separate processes, or one combined process, for the investigation of incidents and the review of nonconformities. “Dürfen”. The examples of incidents, nonconformities and corrective actions, including a fall, protective equipment that does not function, and the use of the hierarchy, are not copied out as a catalogue of types. The guidance describes cause analysis as an investigation of the factors, asking what happened, how and why, with the emphasis on prevention. The organization should use procedures appropriate to the nature of the incident or the nonconformity. The review of effectiveness is said to relate to the extent to which the actions control the causes. “Sollte”.
10.3 requires suitability, adequacy and effectiveness to be continually improved by:
a) enhancing OH&S performance;
b) promoting a culture that supports the system;
c) promoting the participation of workers in carrying out actions for continual improvement;
d) communicating the relevant results of continual improvement to workers and, where they exist, to their representatives;
e) maintaining and retaining documented information as evidence of continual improvement.
A.10.1, guidance: when taking action for improvement, the organization should consider the results of the analysis and evaluation of OH&S performance, of the compliance evaluation, of the internal audits and of the management review. Examples of improvement are said to be corrective action, continual improvement, breakthrough change, innovation and reorganization. A.10.3 names further examples, including new technology, good practice, suggestions from interested parties and new knowledge. Both are guidance. The requirements are 10.1 and 10.3.
5.4 e 7 places the emphasis of the participation of non-managerial workers on investigating incidents and nonconformities and on determining corrective actions. 5.4 d 9 places the emphasis of consultation on ensuring continual improvement.
Documented information: 10.2 requires documented information to be retained as evidence of the nature of the incidents or nonconformities and of any subsequent actions taken, and as evidence of the results of any action and corrective action, including their effectiveness. This information is to be communicated, as 10.2 states. 10.3 e requires documented information to be maintained and retained as evidence of continual improvement.
Not in this text: a root-cause method, a time limit in days, and the equating of an incident with a nonconformity. Note 3 to 3.35 keeps them apart. The arrangement of 10.1 as continual improvement and 10.2 as nonconformity in ISO 9001:2026 and ISO 14001:2026 is not the arrangement of this document.