Explanations of ISO 14001:2026
The source is ISO 14001:2026(en), fourth edition, April 2026, English text. Title: Environmental management systems — Requirements with…
Read articleISO 14001:2026
For: V, IA
Source: ISO 14001:2026(en), fourth edition, English. 3.2.10, 6.1.1, 6.1.4, 6.1.5, A.6.1.1, A.6.1.4, A.6.1.5
3.2.10 defines risks and opportunities as one term: potential adverse effects, that is risks, and potential beneficial effects, that is opportunities. A definition of "risk" alone does not stand in the requirements. A.3 says that the definition of "risk" from the previous edition has been removed, because the word is not used on its own in the requirements. ISO 9001:2026 separates the actions on risks and on opportunities into two subclauses. This document does not. Here both stand in 6.1.4, and the planning of actions in 6.1.5 addresses significant environmental aspects, compliance obligations, and risks and opportunities together.
6.1.4. When planning the environmental management system, the organization shall consider: the external and internal issues from 4.1; the relevant needs and expectations of interested parties from 4.2; the scope from 4.3. "Consider" stands here. According to A.3, the subject shall be thought through, but it can be excluded. And it shall determine the risks and opportunities for the organization that are related to its environmental aspects, its compliance obligations and other issues and requirements identified in 4.1 and 4.2, if any, and that shall be addressed in order to:
The risks and opportunities that shall be addressed shall be available as documented information. Not every conceivable effect shall be addressed. What is documented are those that shall be addressed.
A.6.1.1 says as guidance that there is no particular method, no particular number of steps and no particular process. The organization can use one process for aspects and impacts and another for risks and opportunities, or one process that covers both. A.6.1.4 says as guidance that the organization retains the authority to determine which risks or opportunities it addresses, on the basis of its ability to mitigate risks and to take opportunities. It may choose the method and the degree of formality, from a simple qualitative process to a comprehensive quantitative assessment. The Annex gives examples of risks and opportunities with potential beneficial effects and with potential adverse effects, including effects of climate change on the organization's values. These are examples in the guidance, not a mandatory list. The process can be connected with other processes, including the determination of environmental aspects. The risks and opportunities that shall be addressed are inputs to the planning of actions and to the environmental objectives.
6.1.5. The organization shall plan to take actions in order to address: its significant environmental aspects from 6.1.2; its compliance obligations from 6.1.3; its risks and opportunities from 6.1.4. It shall plan how to implement the actions into the processes of the environmental management system, with a reference to 6.2, clause 7, clause 8 and 9.1, or how to integrate the actions into other business processes. It shall plan how to evaluate the effectiveness of these actions, with a reference to 9.1. When planning these actions, it shall consider its technological options and its financial, operational and business requirements. "Consider" stands here again.
A.6.1.5 explains as guidance that the organization need not assign actions to all risks and opportunities immediately and at the same time. It can prioritize which actions it takes and when, on the basis of business needs and environmental objectives. Planned actions can enter the processes named individually or in combination. Some actions can run through other management systems, such as energy, occupational health and safety, quality or business continuity, or through other business processes. For the technological options, the organization should consider the use of the best available techniques where that is judged to be economically viable, cost-effective and appropriate. This is not intended to mean that organizations would have to apply environmental cost accounting. "Should" and this explanation are guidance.
6.1.1 requires the processes for 6.1.2 to 6.1.5 and their availability as documented information to the extent needed in order to have confidence that they are carried out as planned.
Documented information: The risks and opportunities that shall be addressed. The evidence of the processes from 6.1.1 to the extent needed. 6.1.5 itself names no further documented information.
Not in this text: a risk matrix, an obligation to keep risks and opportunities in separate action plans, and the catalogues of examples from A.6.1.4 as a required list.