The source is ISO 14001:2026(en), fourth edition, April 2026, English text. Title: Environmental management systems — Requirements with…
Read articleISO 14001:2026
For: IA, V
Source: ISO 14001:2026(en), fourth edition, English. 3.4.1, 9.2, 9.3, A.9.2, A.9.3
Audit as a term. 3.4.1 defines an audit as a systematic and independent process for obtaining evidence and evaluating it objectively in order to determine the extent to which the audit criteria are fulfilled. Notes distinguish an internal audit, an audit by a second or a third party, and combined audits. An internal audit is conducted by the organization itself or by an external party on its behalf. Note 3 refers to ISO 19011 for audit evidence and audit criteria. This edition is not available. Note 4: independence can be demonstrated by freedom from responsibility for the activity being audited, or by freedom from bias and conflict of interest.
9.2.1. The organization shall conduct internal audits at planned intervals in order to provide information on whether the environmental management system conforms to the organization’s own requirements and to the requirements of this document, and whether it is effectively implemented and maintained.
9.2.2. It shall establish, implement and maintain one or more internal audit programmes, including frequency, methods, responsibilities, planning requirements and reporting. When establishing them, it shall consider the environmental importance of the processes concerned, changes that affect the organization, and the results of previous audits. According to A.3, “consider” allows a topic to be excluded after it has been thought through. The three subjects shall be thought through. It shall define the objectives, the criteria and the scope for each audit. It shall select auditors and conduct audits so that objectivity and the impartiality of the audit process are ensured. It shall ensure that the results are reported to relevant management. A time limit for corrective actions is not stated in 9.2.2. A.9.2 says, as guidance, that nonconformities identified in the internal audit are subject to appropriate corrective action. The requirement, when a nonconformity occurs, is in 10.2.
A.9.2 explains audit evidence as records, statements of fact or other information that is relevant to the audit criteria and verifiable. Audit criteria are the set of policies, procedures or requirements against which the evidence is compared. Auditors should be independent of the activity being audited, where practicable, and should in every case act free from bias and conflict of interest. “Should” is the recommendation. For previous audits, the organization should include nonconformities identified earlier in internal and external audits and the effectiveness of the actions taken. For establishing a programme, conducting audits of the environmental management system and evaluating the competence of the audit personnel, the Annex refers to ISO 19011. A certification audit is an audit by a third party. 9.2 does not govern its course.
9.3.1. Top management shall review the environmental management system at planned intervals in order to ensure its continuing suitability, adequacy and effectiveness.
9.3.2 Inputs. The inputs shall include:
The fulfilment of compliance obligations is trend information of its own, alongside the monitoring and measurement results. All of the inputs named belong to the review, as they are written.
9.3.3 Results. The results shall include:
A.9.3 explains, as guidance: suitability is how the system fits the organization, its activities, its culture and its business systems. Adequacy is whether it fulfils the requirements of this document and is adequately implemented. Effectiveness is whether it achieves the desired results. The review need not cover every detail. The topics need not be addressed all at once. The review can run over a period of time and be part of other management meetings. It need not be an event of its own. Relevant communications, including complaints, are reviewed in order to determine opportunities for improvement. Where the intended results have not been achieved, top management should consider that when it decides on changes.
Documented information: The audit programme or the audit programmes shall be available, together with the evidence of the implementation of the programme and the evidence of the audit results. For the management review, documented information shall be available as evidence of the results.
Not in this text: an audit programme of a certification body, audit time, and a checklist. ISO 19011 is not retold. The inputs are not equated with those of ISO 9001:2026. They stand here as 9.3.2 names them.